Jalisco plans fewer water rotations from Dec. 15 and Miravalle plant running in April 2027

Story summary: The state government laid out its water works schedule: fewer supply rotations in Guadalajara from Dec. 15 and the new MXN 7.5 billion Miravalle plant operating in April 2027, paid with state funds.

By

How this story was made

How we work →
  • 8 sources
  • 5 outlets compared
Verified on Nov 25, 2026
Cover image for the story: Jalisco plans fewer water rotations from Dec. 15 and Miravalle plant running in April 2027
In this story

What happened

On November 25, 2026, at the second meeting of its Water Advisory Council, the Jalisco state government presented the schedule for the works meant to restore water supply in the Guadalajara Metropolitan Area (AMG). According to state government information published by Quiero TV, the state plans to start reducing service rotation, the rolling water cuts known locally as tandeos, on December 15, 20261. The new Water Treatment Plant 1, in Miravalle, would finish its first stage in March 2027 and start operating in April, after a stabilization period2.

Governor Pablo Lemus told the Council that the state is putting MXN 10.2 billion of its own funds into these works, with no public debt or rate increase, according to Quiero TV3. The figure is not new: Lemus gave it on October 28 at President Claudia Sheinbaum's press conference, according to the Presidency's transcript, and said that day that the state will invest about MXN 7.5 billion in the Miravalle plant33. What is new is the timeline.

What it means for Jalisco

Miravalle is the piece that matters most: it supplies about 42% of the network run by SIAPA, the metro water utility, according to La Crónica de Hoy, and its old system, some 70 years old, carried about 2.5 cubic meters per second4. In March 2026, sediment from the Las Pintas dam degraded water quality and that flow fell to 1.54. Lemus said the new plant will recover about 2,100 of the 2,500 liters per second of lost conveyance capacity, according to Quadratín Jalisco1.

For businesses, the schedule is the variable to watch. Coparmex Jalisco, the state chapter of Mexico's employers' confederation, estimated in late October that the areas under rotation hold 112,801 business establishments, 110,923 of them small and mid-sized, linked to about 820,000 jobs5. December 15 is the announced date to start reducing rotation and the plant is planned for April; the government has not said how much the rotations will fall or in which areas21.

The state package also includes a bypass between the La Calera pumping system and the plant, costing about MXN 1.2 billion6, and Pumping Plant 2, at Las Pintas in Tlaquepaque, whose first two systems add about 1,360 liters per second6.

The long-term aqueducts, Calderón–San Gaspar and Chapala–Guadalajara, depend on the federal government. On October 28, at the same press conference, the director of Conagua, the national water commission, Efraín Morales, reported a federal investment of MXN 14.5 billion across the two projects3; on October 21, ranges of MXN 12 billion to 13 billion had been reported, according to Publimetro7. The 2027 federal budget reallocates MXN 6.5 billion within Conagua to get them started8.

How it is being read

The state government describes Miravalle as "una obra edificada desde cero" (a project built from scratch) that will "reducir de una manera drástica los tandeos" (drastically reduce the rotations), in Lemus's words as reported by Quadratín Jalisco1. Its financial argument is that the package is covered with the state's own funds3.

Coparmex Jalisco set out its position on October 29, before this announcement. Its president, Luis Beas Gutiérrez, said "para miles de negocios, contar con agua es indispensable para trabajar todos los días" (for thousands of businesses, having water is essential to work every day), and called for alternative supply for businesses during rotations and timely information5. As of publication, the organization had not taken a position on the November 25 schedule.

The numbers

  • MXN 10.2 billion in state funds for AMG water works, according to Lemus (October 28 and November 25)3.

  • About MXN 7.5 billion in state funds for the new Miravalle plant, according to Lemus (October 28)3.

  • MXN 14.5 billion in federal funds across two projects, according to the director of Conagua (October 28)3.

  • 2,000 liters per second in the plant's first phase, with operation planned for April 2027, according to La Crónica de Hoy2.

  • About MXN 1.2 billion for the La Calera–Plant 1 bypass6.

  • MXN 6.5 billion in the 2027 federal budget to start the two aqueducts8.

What is not known

  • How much the federal government will contribute in total to the aqueducts: on October 28 Conagua estimated MXN 14.5 billion and the 2027 federal budget only allocates MXN 6.5 billion to start them; no agreement has been published.

  • Which company is building the Miravalle plant and what its total capacity will be; only the first phase has been disclosed.

  • How much rotations will be reduced from December 15, and in which areas.

  • Which budget lines cover the MXN 10.2 billion: there is no public breakdown beyond the plant and the bypass.

Sources (8)

Each number in the text leads to its source. Primary sources are official documents, public data or the companies' own reports.

  1. 1Quadratín Jalisco, Invierte Gobierno de Jalisco en nueva planta potabilizadora de Miravalle (25-nov-2026)accessed Nov 25, 2026↩
  2. 2La Crónica de Hoy (9-oct-2026) y Quiero TV (25-nov-2026)accessed Nov 25, 2026↩
  3. 3Presidencia de la República, Versión estenográfica de la conferencia de prensa de la presidenta Claudia Sheinbaum Pardo del 28 de octubre de 2026primary source · accessed Nov 25, 2026↩
  4. 4La Crónica de Hoy, Jalisco destina más de 8 mil millones de pesos para modernizar infraestructura hídrica (4-nov-2026)accessed Nov 25, 2026↩
  5. 5Plano Informativo (reproduce Reforma), Sin agua no hay empleos: Coparmex busca proteger 820 mil empleos (29-oct-2026)accessed Nov 25, 2026↩
  6. 6Quiero TV (25-nov-2026)accessed Nov 25, 2026↩
  7. 7Publimetro, Federación y Jalisco invertirán hasta 25 mil mdp para mejorar el agua de Guadalajara (21-oct-2026)accessed Nov 25, 2026↩
  8. 8Gaceta Parlamentaria No. 7163-IV (9-nov-2026), Dictamen de la Comisión de Presupuesto y Cuenta Pública con proyecto de PEF 2027, p. 181primary source · accessed Nov 11, 2026↩

How it was covered (5)

Outlets that published this story and where their information comes from. It is a count, not a rating of the outlets.

2 of 5 outlets rely on an official press release
  • Official release 2
  • Company statement 1
  • Own reporting 2